What is the default sort for the project tasks list.
If you click into a project and view the list of tasks contained within it, the tasks are by default sorted on the "Start Date" of the tasks with respect to any existing parent child relationships.
Task Name Start Date
Example:
Task Name Start Date
- My 1st Task 01/01/2008
- My 2nd Task 02/02/2008
- Child Task 1 02/03/2008
- Child Task 2 02/04/2008
- My 3rd Task 02/02/2008
Note:
You can re-sort the task list view by clicking on many of the column headers.